More than a year after the government signed the deal to buy 36 Rafale combat jets in September 2016, the contract is back in the news again, thanks to the allegations by the Opposition Congress that the government did not follow rules and procedures and that it overpaid for the fighters. The allegations have been denied by the government and rightly so. To begin with the previous UPA government had not finalised the price of the contract. So comparison of cost is incorrect. But there is more. the Mod under then Defence Minister AK Antony had convoluted the process to an extent where it had become impossible to go through with the deal in its original format. I have detailed the decade-long journey of what was once described as 'mother of all deals,' in my book Securing India The Modi way: Pathankot, Surgical Strikes and more. Here are the excerpts, in two parts which sheds light on what exactly happened in the Rafale deal.
The competition to
acquire 126 Medium Multi Role Combat Aircraft (MMRCA) for the Indian Air Force
began in 2007 after the government agreed with the IAF that it needed to
replace the aging fleet of MiG aircraft.
Six companies across the world
were issued the tender papers. They were: EADS from Germany, manufacturers of
the Eurofighter Typhoon; Lockheed Martin (who make the F-16s) and Boeing ((F-18
aircraft) from the USA, Sweden’s SAAB (makers of Gripen); Dassualt Aviation
from France (the Rafale manufacturers) and Russia’s Rosoboron Export (MiG-35).
India was looking for 18
aircraft to be bought off the shelf and 108 were to be manufactured in India
(with a local partner, in this case, it was supposed to be the state-owned
Hindustan Aeronautics Ltd). Required maintenance, repair and overhaul
facilities were to be set up. The MMRCA contract was variously described as ‘mother
of all deals,’ ‘most complex defence contract,’ etc in the media reports. And
it indeed was.
According to official
documents that I have had a chance to read, the MoD had in 2011, bench marked
the Total Cost of Acquisition at Rs 163,403 crores. This, it must be pointed
out, was different from the total cost of deliverables in the 126 MMRCA contract, which was bench marked by
the MoD at Rs 69,456 crores, excluding the offset loading cost, estimated to be
anywhere between Rs 2530 crores to Rs 5060 crores.
All this came after the six
companies submitted their techno-commercial bids in April 2008, followed by
nearly 11 months of field evaluation trial (FET) held in the heat of Rajasthan
desert during peak summer months and extreme cold conditions in the high
altitude zone of Ladakh. The trials were completed in May 2010. The evaluation
committee of the IAF shortlisted two aircraft—the Eurofighter Typhoon and the
Rafale aircraft fielded by the Dassault Aviation (DA)—and forwarded the
recommendation to Defence Minister AK Antony. Antony took almost a year to
accept the recommendation. It was already 2011. After prolonged internal
discussions in two sub-committees (the Technical Oversight Committee-TOC, the
Technical Offset Evaluation Committee-TOEC), a Contract Negotiations Committee
(CNC) was formed in April 2011. By September that year, the CNC had arrived at
the benchmarking cost after applying escalation rates by averaging simple
year-on-year escalation.
But it was not before
July 2012, that the CNC activated four Sub-Committees, the 'Maintenance',
`Offset', and `ToT and `Contract' Sub-Committees.
For the next two years, negotiations on Transfer of
Technology, Offset and Maintenance went on apace. However, certain aspects
related to License Manufacture of 108 aircraft in India with HAL as the lead
production agency could not be finalized. Major differences occurred on the
aspect of Man Hours that would be required to produce the aircraft from kits in
India and who would take the responsibility for entire lot of 126 aircraft.
While DA maintained that 31 Million Man Hours that it has proposed should be
sufficient to produce 108 Rafale aircraft in India, HAL was asking for mark up
of this Man Hours by 2.7 times.
This point became the
bone of contention between the government and the French manufacturer.
Moreover, in the understanding of the MoD, the company that
had emerged as the winner in the bid—Dassault Aviation—would have to sign a
single contract with the Indian government. The French Company would then need
to have back to back contract(s) with HAL and other Indian Production Agencies.
Dassault Aviation would also be responsible for the delivery of the complete
126 aircraft to IAF and the single point responsibility for this contract
rested with Dassault Aviation because the RFP was issued to them. At that
stage, the representatives of Dassault Aviation agreed do their best to meet
all requirements of the project as envisaged in the RFP.
However, Dassault Aviation did not fulfil the commitment
given in the first meeting and an impasse ensued on the responsibility of
delivery of 108 aircraft to be manufactured in India. Another hurdle came up on
the point of work share of HAL. Dassault Aviation was asked to submit a
'Responsibility Matrix', clearly defining the role and responsibility of
Dassault Aviation and HAL. The `Responsibility Matrix' was to facilitate a back
to back contract of Dassault Aviation with HAL.
The CNC was however not able to move the negotiations forward since the
interpretation of two fundamental aspects of the case by the French Company was
not in line with the terms of the original terms in the tender.
The first aspect related to treating Dassault Aviation as
the 'Seller' of 126 aircraft, including 108 to be manufactured in India and the
corresponding contractual obligations and liabilities. The second point was
about the ‘man hours for the aircraft to be manufactured in India. The UPA
government, under the overly cautious AK Antony instead of imposing a deadline
for the French manufacturer to comply with the terms of the RFP, dragged its
feet and allowed Dassault Aviation to get away with obfuscation. Moreover, in
an unusual move, Antony instructed MoD officials to bring the file back to him
after concluding the CNC to re-examine
the integrity of the process before proceeding to finalise the contract,
creating confusion and doubt in the minds of the officials who were negotiating
with the manufacturer.
Even as talks got deadlocked, the government changed in
Delhi.
(Continued in Part II)
No comments:
Post a Comment